Contiguous Bored Pile Wall

Closely spaced piles used to form retaining walls in areas where water inflows are not significant. Their main use is in clay soils and may also be used to retain dry granular materials or fills. In water bearing granular soils, seepage is likely to occur in the gaps between the piles which can be prevented by grouting these gaps to form a watertight retaining wall.

Top

Secant Bored Pile Wall

Secant piles are interlocking piles that form a continuous watertight wall. A continuous reinforced concrete guide wall is constructed to pinpoint the location of each overlapping pile. Piles are spaced a distance which is a little less than one pile diameter. The exact spacing depends on construction tolerances.

Alternate piles (known as "female", "intermediate" or "secondary" piles) are drilled inside temporary steel casing and constructed without reinforcement using a slow setting concrete. Temporary casing is extracted while the concrete has not fully set and heavy casing is then driven into the intervening pile location cutting into the fresh concrete of the adjacent female piles. The "male", "primary" or "king" piles are then promptly drilled. The male pile steel cage reinforcement is inserted and structural concrete is poured adhering to the female pile concrete on either side to form a watertight continuous wall.

Top

Sheet Pile Wall

Sheet piles are a series of panels that vertically interlock to form a continuous impermeable wall. The reusable panels can be made from a variety of materials such as steel, wood, plastic and fiberglass. These panels are driven into ground using a vibratory hammer in such a way that each panel interlocks with the adjacent one on each side.

Sheet piling provides an efficient, economical and timesaving solution in certain types of applications such as cofferdams, cut and cover tunnels, retaining walls, seawalls and containment walls. They are however; constrained by the depth of excavation, the magnitude of the lateral pressures, and the stratum they can penetrate.

Top

Soldier / King Pile

Soldier piles, are steel wide flange piles spaced about 1 - 3 m apart. They are driven into the ground prior to excavation by a vibratory or impact hammer or may be installed in drilled shafts and backfilled with concrete. Their main purpose is to provide permanent or temporary shoring for vertical excavation.

After insertion into the ground, the area between each two piles is excavated and timber, steel or pre-cast reinforced concrete panel lagging is inserted behind the H pile flanges. The void space behind the lagging is then backfilled and compacted. Lateral earth pressures are transferred from the lagging onto the soldier piles. In high water table conditions, an extensive dewatering scheme is required with this type of retention system.

Top

Diaphragm walls

Diaphragm walls are formed from cast-in-place reinforced concrete panels with interlocking vertical joints that provide a continuous watertight barrier.

A shallow reinforced concrete guide walls is constructed along the line of the required wall to direct the excavation equipment. Alternating trenches are excavated using specialized equipment and utilizing bentonite slurry to support the vertical walls of the trough preventing soil incursions. The bentonite slurry is continuously circulated and cleaned during excavation. Stop-end pipes are placed vertically at each end of the primary panel to form joints for adjacent secondary panels. Upon completion of the excavation, a steel reinforcement cage is lowered into the trench. Concrete is continuously pumped starting at the bottom of the excavation using a tremie pipe which is extracted as the concrete rises while its discharge end remains immersed in the fresh concrete. The poured concrete displaces the bentonite slurry, which is gradually pumped out, filtered and saved to be reused.

An alternate construction method would be to use pre-cast reinforced concrete panels. The panels are lowered into the trench filled with self-hardening bentonite slurry. The cement bentonite slurry sets adhering to the panels and thus forming the final composite wall panel.

Diaphragm walls are installed without dewatering in a vibration free, low noise process which makes them an ideal solution for congested areas and can be installed in close proximity to existing structures with minimal disturbance to adjacent foundations.

Top

Anchors and Tiebacks

Retaining walls may themselves require further support dependent on design variables such as the depth of the excavation, the magnitude of lateral pressures and characteristics of the surrounding land. This further support restricts lateral deflections and can be achieved by anchors and tiebacks.

Stressed anchors (tiebacks) are constructed by drilling holes through the wall and into the adjacent ground at a downward inclination. The diameter, depth, inclination angle, location and the number of tiebacks are predetermined by design engineers. Steel strand cables (tieback cables) are inserted into the drilled hole which is then pressure grouted with concrete. Once the concrete has set, a strand gripper and gripper casing is placed over the cables and tensioned using a hydraulic jack. Horizontal steel walers may be used across rows of tiebacks.

Top