Driven Piles

Prefabricated steel, wood or concrete piles are driven into the ground using impact hammers. Driven piles provide the fastest deep foundation solution. Driven piles provide the advantage over drilled shaft piles of higher skin friction, thus increasing their load-bearing capacity. They are suitable for most land and marine applications, and offer a high performance piling system with up to 1,000 tons/pile design load capacity.

Steel piles such as sheet and H-beam piles (soldier piles) to form earth retention and excavation support walls, are the most commonly used. Wood and reinforced concrete are used in other limited conditions.

Top

Cast in-Situ Bored Pile

This type of pile installation is used to replace soil removed by drilling rather than occupying the space of displaced soil as in driven piles and thus, it mostly relies on end-bearing capacity of the earth layer at the drilled depth.

One method of installation is to drill a shaft using a continuous auger with a hollow stem at its center which is later used to grout the drilled shaft. This method is known as Continuous Flight Auger.

Another technique is to drill the shaft, insert the reinforcement steel cage (if required) and then pour concrete under pressure to fill the entire shaft space. The shaft is drilled using an auger in dry land conditions and a drilling bucket in wet land conditions.

When shaft wall support is required, the drilling process takes place inside a steel casing or with the aid of drilling slurry such as Bentonite.

Steel drill casing is advanced into the ground using a vibro-hammer; leaving a 1 meter protrusion. After drilling, the steel cage reinforcement is placed within the borehole using a crane and concrete is poured in the borehole under high pressure using a tremie. The temporary casing is then gradually extracted from the ground by vibrating, oscillating or rotating and load is transferred to the formed concrete pile shaft.

In situations where the use of steel casing is not feasible, a drilling mud such as bentonite slurry in utilized for drilling support. A positive head of bentonite suspension above the water table is maintained during the drilling process, thus providing continual support to the borehole walls. Fluid concrete displaces the clean bentonite which is collected and reused several times before it is discarded.

Top

Continuous Flight Auger (CFA) Piles

This method combines all major piling operations in a single process and hence it provides for a highly productive, cost-effective solution that facilitates fast, noise and vibration free piling installation. CFA is implemented in soft to medium strength rock and in sand, gravel or slit land with ample adhesion and end-bearing strength.

A continuous flight auger with a hollow stem at its center is utilized for the drilling process. The end of the hollow stem is sealed with an expendable cap to prevent contamination. During the drilling process drilled matter rests at the top of the auger flights maintaining positive pressure at the shaft walls and thus providing it with lateral support and stability. After reaching the desired drilling depth, concrete is pumped at a controlled rate through the hollow stem blowing off the expendable cap. The auger is simultaneously withdrawn at a rate synchronized with the concrete pumping process such that the pumped concrete promptly occupies the displaced volume exerting a positive pressure which assists in the extraction process whilst maintaining lateral support to the surrounding soils. The steel reinforcing cage (if required) is then immersed into the wet concrete. Typical CFA applications are for a maximum pile depth of 12m and 600mm diameter. However, larger pile dimensions can be achieved.

Top

Pile Caps and Capping Beams

Pile caps connect groups of piles to distribute loads over the capped piles. Pile heads are stripped to expose the steel reinforcement to be projected into the pile cap. Steel reinforcement is placed at the desired location and a large concrete block is formed. Pile caps can assume a variety of shapes, but they are mostly rectangular or triangular.

Top